Naenae Pool & Fitness Centre progress update

A photo of the interior of the Naenae Olympic Pool banner image

Published: 16 April 2024

Here’s a taste of the great progress being made at the site of the Naenae Pool and Fitness Centre as we get into the internal fitout.

The roof is now sufficiently complete for work to progress underneath. Removing the scaffolding from the Leisure Pool Hall is a major step forward to completing the leisure pool and hydro-slides (zoom tubes).

The $68m project received co-funding of $27m from Crown Infrastructure Partners to help make this wonderful new asset in Naenae possible.

Inside Naenae Pool April 2024

Wall framing between Change Rooms and Leisure Pool Hall.

A photo of the interior of the Naenae Olympic Pool

Main pool lane marking nearing completion.

Inside Naenae Pool looking at the zoom tubes, April 2024.

Interior hydro slide unit and frames being installed.

Inside Naenae Pool April 2024

Services, painting works and moveable floor preparation in the Main Pool Hall.

Inside Naenae Pool April 2024

View progress in real time with our time lapse cameras here: hutt.city/timelapse.

Find out the latest news on our Naenae projects by signing up to our newsletter here: hutt.city/naenaenewsletter