Hutt City Council has appointed Moore Construction to deliver the next stage of work to improve the resilience of Eastern Hutt Road. Work is expected to start from 30 November 2026.
Moore Construction is a New Zealand-owned company with extensive experience in piling and complex civil construction projects.
Mayor Ken Laban says it's great to see the next stage of work, just north of the Stokes Valley roundabout, getting underway.
"Eastern Hutt Road is a vital connection for our communities, with around 10,000 vehicles using it every day. It’s important we get this work done now, to make the road safer and more resilient for the future.”
The work will focus on strengthening the slope below Eastern Hutt Road, with 64 reinforced concrete piles and 110 ground anchors being installed to help stabilise the road.
To keep traffic moving and minimise disruption, this stage of work has specifically been designed to take place off the road as much as possible, utilising and widening the existing Hutt River Trail as a construction platform.
A temporary speed restriction will be in place, and some lane closures will be needed to move equipment and materials on site. Where possible, lane closures will be scheduled outside peak traffic times. Some work may also take place at night where it’s safe and practical.
An alternative route will be available for Hutt River Trail users during construction.
Moore Construction is working with local contractors where possible and sourcing materials such as concrete, reinforcing steel and aggregates from local suppliers.
We'll continue to provide updates as work progresses and give advance notice of any significant traffic changes.
Once the below-road work is complete, the project will move to strengthening the slopes above Eastern Hutt Road in 2027.
For more information and to sign up for the project newsletter, visit Eastern Hutt Road Resilience.